The Seasonal Calendar: When the Work Happens
The most critical parameter for renovation in Antalya is the start date. For rented or seasonally used apartments the working window is effectively November to March; miss it and the work either happens in season at the cost of lost income, or slips by a year. The programme is therefore built backwards: fix the handover date, order long-lead items — kitchens, joinery, bespoke furniture — early against it, and set the site programme on top. If working in season is unavoidable, remember neighbouring apartments are occupied: restrictions on noisy work and debris removal have to be accepted.
- Planning the working window for November to March
- Building the programme backwards from the handover date
- Ordering long-lead items before site work begins
- Accepting noise and debris restrictions for in-season work
- Costing delay in seasons rather than in days